Adelaide Oval has enjoyed a proud history as one of Australia’s premier sporting and entertainment venues for more than 140 years.

In late 2009, the State Government committed $535 million to redevelop Adelaide Oval with the view to delivering an internationally renowned, world-class venue for the 21st Century. 

The opening of the redeveloped Adelaide Oval has seen it once again sit proudly within a revitalised riverbank and parklands precinct; home to cricket, football and provides an exceptional venue for a host of other major sporting events and entertainment.

Project timeframe

Major construction works commenced in the first quarter of 2012. The following is a summary of the key construction activities and their completion dates.

Timeframe Activity
December 2011 Service relocation
February 2012 Site Establishment
March – September 2012 Northern mound and ancillary works
March 2012 – November 2013 Riverbank Stand and Telstra Plaza
March 2012 – March 2014 Eastern Stand
March 2012 – March 2014 Indoor Centre
March 2013 – October 2013 Main Oval Works
March 2014 Project Completion